05 — ACTIVITY DURATION ESTIMATION
Estimated Project Schedule
The following table presents the estimated duration of each major project activity.
| # | Activity | Duration | Schedule |
|---|---|---|---|
| 01 | Project Initiation | 1 Week | Week 1 |
| 02 | Requirements Analysis | 2 Weeks | Weeks 2–3 |
| 03 | System Planning & Design | 2 Weeks | Weeks 4–5 |
| 04 | UI/UX Design | 1 Week | Week 5 |
| 05 | System Development | 4 Weeks | Weeks 6–9 |
| 06 | System Integration | 1 Week | Week 9 |
| 07 | System Testing | 1 Week | Week 10 |
| 08 | Revision & Improvement | 1 Week | Week 11 |
| 09 | Finalization | 1 Week | Week 12 |
