Estimated Project Schedule

The following table presents the estimated duration of each major project activity.

# Activity Duration Schedule
01 Project Initiation 1 Week Week 1
02 Requirements Analysis 2 Weeks Weeks 2–3
03 System Planning & Design 2 Weeks Weeks 4–5
04 UI/UX Design 1 Week Week 5
05 System Development 4 Weeks Weeks 6–9
06 System Integration 1 Week Week 9
07 System Testing 1 Week Week 10
08 Revision & Improvement 1 Week Week 11
09 Finalization 1 Week Week 12